Fresno County lands what reportedly will be West Coast’s largest green hydrogen plant

Fresno County will be home to what a New York company says will be the largest green hydrogen production facility on the West Coast. Officials with Plug Power, headquartered in Latham, New York, said in their Monday announcement that the plant — near Mendota — is expected to produce 30 metric tons of liquid green hydrogen daily within about four years.

The facility will use a new 300 megawatt zero-carbon solar farm to power 120 megawatts of Plug Power’s state-of-the-art PEM electrolyzers, which split water into hydrogen and oxygen through an electro-chemical process, the announcement stated. The California plant would join the company’s growing national network of facilities in New York, Tennessee and Georgia that officials say will supply 500 tons per day of liquid green hydrogen by 2025 — replacing, the company states, 4.3 million metric tons of carbon dioxide emissions and 1,000 tons per day globally by 2028.

Work will include construction of a new tertiary wastewater treatment plant in Mendota that will provide recycled water for residents and supply the full needs of the plant. The company hopes to break ground in early 2023 and complete commissioning in early 2024. The company announcement did not specify where the hydrogen plant will be built nor how many people might be hired locally. “The project is a huge win for the city of Mendota, and we are very happy to see this significant investment in clean energy in our community,” Mendota Mayor Rolando Castro said. “This green-hydrogen plant will provide full-time, high-paying jobs for our people. The city will also get a new wastewater treatment plant to provide recycled water for the city and all the needs of the hydrogen plant.”

https://energycentral.com/news/fresno-county-lands-what-reportedly-will-be-west-coasts-largest-green-hydrogen-plant

LATHROP LANDS TESLA MEGA BATTERY PLANT

When Tesla announced that Lathrop would be the site of a plant that manufactures parts for the company’s electric cars in Fremont back in 2014, nobody thought that it would be the beginning of a growing relationship between one of the world’s most closely-followed companies and the growing city. But on Monday the company officially broke ground on a project that will repurpose what was previously a J.C. Penney distribution center for a manufacturing facility for an entirely new product – a massive, trailer-sized battery that will be used not for cars or homes, but to store excess power from the power grid and funnel that power back when it is needed most.

For Lathrop Mayor Sonny Dhaliwal, the announcement of the manufacturing facility for the Megapack – billed by the company as the largest, densest storage battery in the world – is another feather in the cap for the city. “Lathrop is proud to be the home of the Megafactory, Tesla’s most recent expansion here,” Dhaliwal said. “The future of green energy will be produced right here in our community. “This development means more opportunities for our residents, and a brighter future for our planet.” While the company – known the world over for its electric vehicles – has been in the home power storage space for some time, the Megapack will be different because of the unique role that it will play in promoting a greener world by improving power efficiency.

The storage system aims to “transform the way that utilities manage the power grid” by providing “emissions-free” energy when providers need it most – eliminating the need for traditional fossil fuel power plants that are commonly used to supplement shortages. While the delivery of electricity has become more efficient, the distribution of power across long distances often leads to overall loss – especially since traditional grids don’t have any place for excess power that isn’t needed to be stored. The Megapack solves this problem by allowing energy providers with the chance to store that excess power and send it back into the grid as it is needed – something that the company already does with its home-focused battery system that allows for excess power generated by solar panels to be stored and saved.

The facility in Lathrop will assemble and distribute the Megapack units around to locations around the world – including those that are utilized here in California – and will include over-the-air updates to the operating software for the units to maximize efficiency and continuously improve performance. The announcement in 2014 that Tesla would take over the shuttered Mopar distribution facility along I-5 made headlines around the country as the Silicon Valley company expanded its footprint beyond Fremont where it assembles most of its electric cars. But that was just the beginning for the growing South County city and one of the world’s most recognizable brands.

Tesla has since expanded its initial building’s footprint, and added other space including an 870,000 square foot distribution center behind the old Pilkington glass plant on Louise Avenue. A company that manufactures parts that are used in Tesla vehicles also opened a facility in Lathrop near the original Tesla building to help provide parts that are used in the manufacturing process. And for a time, Lathrop also housed thousands of Tesla vehicles that had been assembled in Fremont and were awaiting shipment to their final destination – renting space at the old Pilkington facility to temporarily stage the vehicles that were dropped off and hauled away by trailer.

According to Bloomberg News, the news that Tesla was expanding its operations in California was a welcome sign for the state after the company’s CEO, Elon Musk, slammed the state’s shutdown efforts early during the COVID-19 pandemic and subsequently moved to Texas – which is now where the company plans to assemble the Model Y and Cybertruck vehicles. The move to build the Megapack in Lathrop, Bloomberg said, was seen as a sign that California remains a part of the company’s future.

https://www.mantecabulletin.com/news/local-news/lathrop-lands-tesla-mega-battery-plant/

Major energy storage project proposed near Lebec along California Aqueduct

California’s energy future keeps pointing to Kern. The latest 10-figure energy storage proposal in the county is a damlike “pumped hydro” project connected to the California Aqueduct that would store and release 3,500 gigawatt-hours of power per year on or near Tejon Ranch.

There’s no money yet for it or a similar proposal the same Los Angeles County engineering and development group disclosed in December that would be located next to Isabella Lake. But the latter has attracted interest from one of the world’s largest oil producers, the developer’s managing director said. “The market is very active right now,” Victor Rojas at Walnut-based Premium Energy Holdings LLC said. “There is a lot of storage activity investment and the oil companies are very active, too, and they are seizing now, moving into this energy transmission business.” He declined to identify the oil company his firm is talking with but noted the U.S. Department of Energy is interested, too.

Both of Premium’s pumped-storage proposals are engaged in a federal application process that will succeed only if they can secure big investments — probably a mix of public and private money repaid in time by utility ratepayers — for the kind of infrastructure critical to California’s aggressive transition to renewable energy.

https://www.bakersfield.com/news/major-energy-storage-project-proposed-near-lebec-along-california-aqueduct/article_fd846a78-1db7-11ec-949b-0b62703c0410.html

Amazon opens in Visalia

Amazon is open and in full operation says the new general manager at the Visalia fulfillment center, Carlos Avelar. The 1.3 million square foot warehouse, the largest in the city, is on Riggin and Kelsey in the Visalia Industrial Park. “We have already hired nearly 1,000 on our way to 1,200 associates” said Avelar, adding they are “bringing on more employees than we originally anticipated.”

The original announcement said 1,000 jobs. Avelar said he moved his family to Visalia in July from Tracy where he had been manager for 2.5 years. ”The Central Valley has special place in my heart,” said Avelar, adding that he is looking forward to an open house soon, inviting local officials, and has already huddled with other industry managers at the industrial park to introduce himself. “We want to be part of the community,” he said.

The Visalia Amazon is different from any other Amazon in the Valley, being a “fulfillment center” that stores goods, mostly larger in size, to be shipped throughout the Valley. The closest similar facility is in Patterson, said Avelar. Within these fulfillment centers, associates pick, pack and ship larger-sized customer items ranging from boxes of diapers to patio umbrellas. “We picked Visalia to be close to our customers,” he said.

The next three months will be the busiest of the year for the big e-retailer says the general manager and at times they may add more than 1,200 to the workforce. Employees’ starting pay is at least $15.50 per hour and benefits including paid time off and dental care. New hires who show proof of their COVID-19 vaccination earn a $100 bonus on their first day. Avelar said employees appreciate the fact Amazon encourages associates to go to college and will pay to make it happen while they work here. Avelar said he “has heard the rumors” that there will be a second Amazon warehouse built in the industrial park — but for now ”it’s just that — a rumor.”

https://hanfordsentinel.com/news/local/around-kings-county-amazon-opens-in-visalia/article_78576396-3bbb-5093-a632-bd74476cb549.html

CBRE Global Investors, Trammell Crow to Develop 606,343 SF Logistics Facility in Northern California

CBRE Global Investors has purchased a 29.3-acre site located at 1205 E. Grant Line Road in Tracy for the development of a logistics center. The investment firm will partner with Trammell Crow Co. to develop the 606,343-square-foot facility. Construction is slated to begin in early 2022, with completion scheduled for first quarter 2023.

The distribution facility will feature 40-foot clear heights, 185-foot truck courts, 56-foot by 60-foot column spacing, LED and sky lighting and an ESFR sprinkler system. HPA is serving as architect of record and Big-D Construction is the general contractor.

https://rebusinessonline.com/cbre-global-investors-trammell-crow-to-develop-606343-sf-logistics-facility-in-northern-california/